Duplication of the Viaduct Adib Chammas Works Enter the New Phase
The duplication works of the Adib Chammas viaduct, in Santo André, entered a new stage this week with the beginning of the assembly of the so-called “Advance Cars”, equipment that will be suspended on the avenue of the States in both directions. This phase of construction marks the beginning of the use of the constructive methodology called successive balance.
With the use of this method, it will be possible to duplicate the viaduct without the need to interdict the avenue of the States, avoiding as much as possible harming the mobility of drivers.
The technology allows the construction of the new tracks of both (02) sides of the Adib Chammas,enabling the meeting of the structures for the consolidation of the work. The technique also allows a reduction in the number of supports that would be installed in the soil and that, therefore, would require more time to perform.
In a survey carried out at the construction site, Mayor Paulo Serra highlighted the agility with which the duplication of the viaduct advances. “This innovative method of construction will allow this work to decrease the time of displacement between the first and second subdistricts, increasing fluidity. The Andreenses had been waiting for a work of this size for many years and it will be delivered”, he said.
This innovative method of construction will allow this work to decrease the time of displacement between the first and second subdistricts, increasing fluidity. The Andreenses had been waiting for a work of this size for many years and it will be delivered
Maximum Vehicle Height
In the coming weeks, with the progress of this new phase of works, there will be a need to temporarily reduce the maximum height allowed for vehicles to pass under the Adib Chammas viaduct. Currently this limit is 5.5 meters and will pass to 4.3 meters in the two lanes on the right of the avenue of the States, in both directions, and to 4.7 meters in the other lanes. The Department of Traffic Engineering (DET) will disclose the changes in advance to drivers.
Once the new limit is adopted, which should occur in mid-June, trucks with height between 4.3 and 4.7 meters must necessarily use the two lanes on the left of the avenue of the States. DET agents will provide support at busy times to direct drivers.
In the approach of the work, as a form of safety and to avoid the contact of tall vehicles with the structures running, signs will be installed alerting to height limitation. A height detector system with flashing yellow lights will also be placed on the track, which will alert drivers to the height limit, forcing the vehicle to travel along the left lanes or then by mandatory detour route.
Investment for Duplication Works
The duplication of the Adib Chammas viaduct is part of the mobility works package being carried out in Santo André with funds from the IDB (Inter-American Development Bank). The City Council obtained funding of US$ 25 million from the financial institution and will invest another US$ 25 million in several works, such as the creation of new handles on the Castelo Branco viaduct, which will be completely modernized.
Interview with the Mayor
Mayor evaluation from this time today what has already advanced, what is possible we trace projection? Look we have been trying to anticipate the deadline for the end of 2020 contractually January 2011 we have been working to anticipate this because we want to start the side part of santa terezinha and we can not do the two sent at the same time many people have asked on the highway of the white castle used an ecuperação before n but we can not give people of edict harm the mobility of people so the sooner viaduct that will give its final phase has to be ready earlier we talk the road complex in santa terezinha we have already made all the fronts but now lack the part of the roundabout of the
avenue of the state to talk about this work that today is fast pace 50 , 50 workers here daily sunday weekend – said tonight this work has an advantage beyond the small interference that has in traffic by the size of the work it has no community for the neighborhood do not have residence that not all then you can work on the weekend can work in the night time and that’s what we have done here to try to anticipate this program but the pace is quite satisfactory all the interference that had with you know were resolved of pipelines that pass here and now efe there fan the weather continue helping also we were entering the rainy season the summer but because it is since there is no work that we as soon as possible is delivered on the 12th mayor josé rechuan because he plays is already we’re already seeing here today but he’s not mirrored we’re seeing here is being made to android until earlier there the percentage is in this region for example 27 work doctor installed there the unit will call the subject more than a week is the next ae the creation of the plans and the millions of the 15 million resources of the inter-American development bank bid the total video project is 25 million dollars 12 million reais 15 million reais is the rest of the complete project on holy water have zinha – state and the bus corridors in the city center so this is the package of 12 hours already begins to come out of the research paper sometimes when we can already think for a few months and 34 even the white castle he needs a structural reinforcement and already in the first half of next year the effective work already begins what causes more impact is the handles that will do with the avenue of the states passes in above
the other and then we hope to finish this work start but the route of the diversion will be recovered already from the first half of next year